Review of implementation of recommendations of enquiry committee on Grid
Disturbance and Protection Audit for an Indian power systemGrid
Partager ceci sur
Client
Power Grid Corporation of India Limited
Emplacement
India
Période
2015 - ongoing
Services provided
Study and review of the implementation status for the recommendation of the Enquiry Committee
Study of documents issued by Enquiry Committee (EC) regarding the grid incident (blackout) of July 2012
Detailed protection settings for 77 HV substations and training of PGCIL staff.
Sous-domaines utilisés
Introduction aux sous-domaines utilisés
Sous-stationsPlanification et calcul de réseauxFonctionnement et contrôle
Our website uses cookies to remember your preferences and to help us to provide you with the best experience and to continuously improve our site. By clicking on “Agree and proceed” you are agreeing to us placing cookies on your computer in order to analyse the way you use our website. You can refuse cookies by clicking on “Change settings”.